ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION
ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION Investor: IMMORENT ČR s.r.o., Praha
Locality: Hradec Králové
Investment costs: about 1 mld CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Jiří Dařbuján, Ing. arch. Helena Dařbujánová, Ing. arch. Miloslav Dědek
Construction: Ing. Bohuslav Řičař, Ing. Miroslav Stehno, Ing. Milan Mužík, Ing. František Futera
Supplier: Skanska CZ a.s., Building division Moravia
Part: complex providing of engineering and designing
Realization: 2005-2006
Note: Building was awarded The building of year 2008 and award of public.
ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION ADMINISTRATIVE CENTRE OF HRADEC KRÁLOVÉ REGION
DHL (logistic centre)
DHL (logistic centre) Investor: HOYA, s.r.o.
Locality: Hradec Králové
Investment costs: 150 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno
Part: building contract documention
Realization: 2009
DHL (logistic centre)
REZIDENTIAL HOUSE IN KOUTY
REZIDENTIAL HOUSE IN KOUTY Investor: V KOUTECH, s.r.o.
Locality: Hradec Králové
Investment costs: 100 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno, Martin Široký
Part: building contract documention for area management
Realization: 2009
REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY REZIDENTIAL HOUSE IN KOUTY
GUEST HOUSE
GUEST HOUSE Investor: private persones
Locality: Jánské Lázně
Investment costs: 27 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno
Part: building contract documention for area management
Realization: 2009
GUEST HOUSE GUEST HOUSE GUEST HOUSE GUEST HOUSE
C. BECHSTEIN EUROPE,s.r.o.-rekonstrukce výrobních hal
C. BECHSTEIN EUROPE,s.r.o.-rekonstrukce výrobních hal Investor: C. BECHSTEIN EUROPE,s.r.o.
Locality: Hradec Králové
Investment costs: 50 mil. CZK
Construction: Ing. Bohuslav Řičař, Ing.Miroslav Stehno
Part: building contract documention, observation of the work, realization
Realization: 2009
 
SPORT CENTRE
SPORT CENTRE Investor: Ministry of the interior of the Czech Republic
Locality: Hradec Králové
Investment costs: 11 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno, Martin Široký
Part: projektová dokumentace, autorský dozor
Realization: 2009
 
KATSCHNERKA (parking house)
KATSCHNERKA (parking house) Investor: ATOL, a.s.
Locality: Hradec Králové
Investment costs: 110 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno, Martin Široký
Part: building contract documention, observation of the work
Realization: 2008 (kolaudace 2009)
KATSCHNERKA (parking house) KATSCHNERKA (parking house) KATSCHNERKA (parking house) KATSCHNERKA (parking house) KATSCHNERKA (parking house)
ČLA TRUTNOV
ČLA TRUTNOV Investor: Hradec Králové region
Locality: Trutnov
Investment costs: 50 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno, Martin Široký
Part: building contract documention, observation of the work
Realization: 2008
ČLA TRUTNOV ČLA TRUTNOV
INSTITUTION FOR DEAF-MUTE HRADEC KRÁLOVÉ
INSTITUTION FOR DEAF-MUTE HRADEC KRÁLOVÉ Investor: ZDRAVOTNICKÝ HOLDING, a.s.
Locality: Hradec Králové
Investment costs: 600 mil. CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno
Part: concept, project design
Realization: 2008
INSTITUTION FOR DEAF-MUTE HRADEC KRÁLOVÉ INSTITUTION FOR DEAF-MUTE HRADEC KRÁLOVÉ
RESIDENTAL HOUSE EXTENSION
RESIDENTAL HOUSE EXTENSION Investor: privat persone
Locality: Praha 4
Investment costs: 16 mil. CZK
Structural design: Ing. arch. Pavel Tušl
Construction: Ing. Bohuslav Řičař, Martin Široký
Part: building contract documention
Realization: 2008
RESIDENTAL HOUSE EXTENSION RESIDENTAL HOUSE EXTENSION
ČESKÁ SPOŘITELNA TRUTNOV-branch
ČESKÁ SPOŘITELNA TRUTNOV-branch Investor: Česká spořitelna
Locality: Trutnov
Investment costs: 50 mil. CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno
Part: building contract documention, observation of the work
Realization: 2008 (kolaudace 2009)
 
GREENHOUSE BŘEZHRAD (logistic centre)
GREENHOUSE BŘEZHRAD (logistic centre) Investor: HOYA, s.r.o.
Locality: Hradec Králové
Investment costs: cca 800 mil. CZK
Structural design: Ing. arch. Iva Tušlová
Construction: Ing. Bohuslav Řičar, Ing. Miroslav Stehno
Part: building contract documention
Realization: 2007-2009
 
SCHOPING CENTRE OBI
SCHOPING CENTRE OBI Investor: SALLEROVA VÝSTAVBA
Locality: Hradec Králové
Investment costs: cca 300 mil. CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing.Miroslav Stehno
Part: building contract documention for area management
Realization: 2007
 
PANASONIC
PANASONIC Investor: Matsushita Communication Industral Czech s.r.o., TAKENAKA EUROPE GMBH, pobočka Praha
Locality: Pardubice, Free zone
Investment costs: 1mld CZK
Structural design: TAKENAKA EUROPE GMBH, pobočka Praha
Construction: Ing.Miroslav Stehno, Ing.Bohuslav Řičar
Supplier: TAKENAKA EUROPE GMBH, pobočka Praha
Part: building contract documention
Realization: 1q/2002
PANASONIC PANASONIC
OBCHODNÍ CENTRUM KUKLENY
OBCHODNÍ CENTRUM KUKLENY Investor: RENYSON 2000 a.s.
Locality: Hradec Králové
Investment costs: 450.0 mil.CZK
Structural design: Ing. arch. Pavel Tušl, Ing. arch. Jiří Dařbuján, 2000
Construction: Ing. Bohuslav Řičař, Ing. Miroslav Stehno, 2000
Supplier: SYNER s.r.o., Liberec
Part: building contract documention
Realization: 2000-2001
OBCHODNÍ CENTRUM KUKLENY OBCHODNÍ CENTRUM KUKLENY OBCHODNÍ CENTRUM KUKLENY OBCHODNÍ CENTRUM KUKLENY
POBOČKA IPB
POBOČKA IPB Locality: Trutnov
Investment costs: 40.0 mil.CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Miroslav Stehno
Part: new work including interior design
Realization: 1998
POBOČKA IPB
INTERIÉR ČESKÉ SPOŘITELNY
INTERIÉR ČESKÉ SPOŘITELNY Investor: Česka spořitelna a.s., Praha
Locality: Hradec Králové
Investment costs: 130.0 mil.CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Bohuslav Řičař
Supplier: Orlická stavební a.s., Rychnov nad Kněžnou
Part: interior design
Realization: 1998
INTERIÉR ČESKÉ SPOŘITELNY INTERIÉR ČESKÉ SPOŘITELNY
ČESKÁ SPOŘITELNA a.s.
ČESKÁ SPOŘITELNA a.s. Investor: Česká spořitelna a.s., Praha
Locality: Hradec Králové, tř. ČSA
Investment costs: 130.0 mil.CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Bohuslav Řičař
Supplier: Orlická stavební a.s., Rychnov nad Kněžnou
Part: building contract documention, interior design
Realization: 1998
 
SQUASH CENTRUM
SQUASH CENTRUM Locality: Hradec Králové
Investment costs: 20.0 mil.CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Miloslav Hloucal
Part: new work including interior design
Realization: 1998
SQUASH CENTRUM
NOVOSTAVBA ČESKÉ INSPEKCE ŽIVOTNÍHO PROSTŘEDÍ
NOVOSTAVBA ČESKÉ INSPEKCE ŽIVOTNÍHO PROSTŘEDÍ Investor: České inspekce životního prostředí, Praha
Locality: Hradec Králové
Investment costs: 35.0 mil.CZK
Structural design: Ing. arch. Jiří Dařbuján, 1996
Construction: Ing. Miroslav Stehno, 1997
Supplier: Janák stavební a.s., Hradec Králové
Part: building contract documention, interior design
Realization: 1997-1998
NOVOSTAVBA ČESKÉ INSPEKCE ŽIVOTNÍHO PROSTŘEDÍ NOVOSTAVBA ČESKÉ INSPEKCE ŽIVOTNÍHO PROSTŘEDÍ NOVOSTAVBA ČESKÉ INSPEKCE ŽIVOTNÍHO PROSTŘEDÍ
POBOČKA RAIFEISENBANK
POBOČKA RAIFEISENBANK Locality: Hradec Králové
Investment costs: 35.0 mil.CZK
Structural design: Ing. arch. Miloslav Dědek
Construction: Ing. Bohuslav Řičař
Part: reconstruction including interior design
Realization: 1997